Hydrogen-Aeolic Energy with Optimised eLectrolysers Upstream of Substation

Hydrogen Tank Delivered to Site

On November 5, 2020, one more piece of the puzzle fell into place: the pressurised buffer tank for the electrolyser was delivered to Berlevåg!

While it may look big, this tank is actually only able to take about 4 hours of production from the electrolyser at full power. To save space, it stores hydrogen at 30 times atmospheric pressure, which is also the operating pressure of the electrolyser (so that we do not need a compressor).